Turner/PCL/Flatiron Joint Venture Updated May 14, 2010

The Turner/PCL/Flatiron Joint Venture has begun the process of designing and building a $470,000,000 expansion of Terminal 2 at the San Diego International Airport.

The scope of work includes construction of a three-story, ten gate expansion of Terminal 2 consisting of a ticket lobby, airline check in, security screening, baggage handling, seating areas, concessions and support space. Also included is approximately 1,500,000 sq. ft. of new taxiway and Jet parking. The project is targeting a LEED Silver Certification from the United States Green Building Council upon completion in late 2012. The lead designer under the Joint Venture is HNTB with local Architect Tucker Sadler and Associates providing key support.

The project will be developed using a Progressive Design Build delivery method enabling close collaboration between the Airport Authority and the Joint Venture. A major focus is to involve local contractors and vendors wherever possible to make this landmark project truly a community effort.

The Progressive Design Build Approach allows construction to start even while the highly specialized design is still in progress. Bid packages for the Terminal and the Airside will be staggered as the design advances, with Terminal construction packages bidding through mid 2011. Initial construction work on the Taxiway and Project Management Office is scheduled to start in the late 3rd quarter of 2009, and construction of the Terminal is scheduled to begin by late Summer 2010.

The Project Team looks forward to the participation of the local subcontractor and supplier community throughout the course of the project. By packaging the work into smaller scopes where appropriate, opportunities will be provided for smaller local firms that might otherwise be excluded from a project of this magnitude. In this spirit it will be strongly recommended that all major Trade Contractors provide every opportunity for Small and Disadvantaged firms to participate in this process. This will be a landmark project for San Diego, built for and by the local community!

To find out more information and to participate in prequalification for bidding this work, please register here.

For subcontracting opportunities on the Terminal Development Program, please contact:

Major construction packages under the Turner/PCL/Flatiron Joint Venture are currently scheduled to bid in the following time frames:

Description of Work Area Estimated Value Range Estimated Advertise Date
Baggage Handling Systems Terminal $30,000,000 Q3 2010
Glass Curtainwall - Design Build Terminal $8,300,000 Q3 2010
Elevators and Escalators Terminal $6,400,000 Q3 2010
Network & Security Systems - RFQ Terminal $15,600,000 Q4 2010
Airport IT Systems & Systems Integration Terminal $6,200,000 Q4 2010
 Exterior Enclosure / Fireproofing Terminal $15,400,000 / $1,600,000 Q1 2011
Wall, Ceiling & Interior Framing / Interior Finishes Terminal $14,600,000 / $30,000,000 Q2 2011

Future Scope Opportunity

For future bid opportunities, all information including plans and specifications will be available at the Airport Authority’s BidsOnline system. Prospective bidders are strongly encouraged to register and responsive bidders are required to be registered.

As the major scopes of work draw closer to starting, there will be more specific details posted to the website regarding opportunities. Additionally, identified within each of the scope packages will be supply opportunities.